Step-1 Go to Tools on the menu bar, click “Schedule” or Press F9.
How to change schedule calculation setting to Retained Logic or Progress Override?
This could also be on the advantage side if the effort spent in fixing the logic is worth as the changes made in schedule that project team believes that is achievable and make sense to them.
For example the “Excessive Free Floats” are found or project completion date is shorten significantly.